Lithium – ug hdpe buried piping
Wenco was awarded the installation, testing and pre-commissioning of Underground Pipework
WENCO Scope
Albemarle Kemerton Project- successfully executed with ZERO LTR
- Supply of HDPE Pipes ( 75-315mm) 23 Km
- Installation, testing and pre-commissioning of the Above Ground HDPE Piping – Fire water, Service water and Gas Lines
- Supply and Installation of Isolation Gate Valve (36 nos)
- Installation of In-line valves & Bolt Torqueing
- Installation of all pipe fixings to pipe supports
- Pipe Laying, Testing and Pre-commissioning of UG Piping