Wenco was recently awarded two major projects as listed-below:

Albemarle Kemerton Project (90% Completed)

  • Wenco is involved in the supply, installation, testing and Pre-commissioning of Albemarle Kemerton Plant
  • Complete UG Piping Services - HDPE Piping Supply and Installation for 20 KM (2"-12")

Progress:

  1. Material unloading & workshop set-up complete
  2. Total - 19,386 LM, completed – 15,639 LM
  3. Shop & Field Joints in progress (1731 Joints completed)
  4. Manhours - 10,580 hrs
  5. Practical Completion - 25th Oct 2019

Chevron Wheatstone Project (58% completed)

  • Wenco is involved in the installation, testing and Pre-commissioning of Chevron Utility Water Line
  • GRE Piping Installation, testing and Pre-commissioning for 6 KM AG Utility Water Pipeline
  • Service water
  • Sizes – 2" to 8" 16 bar
  • Taper/Taper Joints

Progress:

  1. Site Joints Completed – 2009 / 3533
  2. Overall progress - 58%
  3. Overall MH – 12,450
  4. Support Installation – 230 /1175
ibc
ibc
Wenco PTY LTD
CONNECT WITH US
Fill out the form below to contact us or request one of our representatives to contact you. Thank you!
Thank You. We will contact you as soon as possible.

Call us at
+61 8 9267 5500

Services Inquiry Form

GET YOUR MONTHLY FIX
of Wenco Group News
Simply drop your details in below and we’ll send the latest Wenco news to your inbox each month.