Onshore & Offshore Projects
Ongoing Live Projects :
Onshore & Offshore Projects
Major Past Projects:
LITHIUM – UG HDPE BURIED PIPING
Wenco was awarded the installation, testing and pre-commissioning of Underground Pipework
Project Key Facts
Project Owner:
Albemarle
Project Name:
Buried – UG HDE Piping
Client:
Wood
Value (AUD):
$2.5M
Year:
2019
WENCO Scope
- Supply of HDPE Pipes ( 75-315mm) 23 Km
- Installation, testing and pre-commissioning of the Above Ground HDPE Piping – Fire water, Service water and Gas Lines
- Supply and Installation of Isolation Gate Valve (36 nos)
- Installation of In-line valves & Bolt Torqueing
- Installation of all pipe fixings to pipe supports
- Pipe Laying, Testing and Pre-commissioning of UG Piping


YARA - SCW Return Header Replacement Project
Wenco was awarded the Design, Installation, Testing and Commissioning of the YARA SCW Return Header Replacement Project
Project Key Facts
Project Owner:
Yara
Project Name:
SCW Return Header Replacement Project
Client:
Yara
Value (AUD):
$4.3M
Year:
2020
WENCO Scope
- Design and Engineering works
- Stress analysis of SCW GRE Piping
- Supply, Pre-fabrication, Installation, Testing and Commissioning of NOV FGS GRVe Pipes and Fittings
- SCW Return Header- 20" to 48" GRVe Piping System
- Hydrostatic testing
- Installation of In-line Valves & Bolt Torqueing
- Installation of all pipe fixings and pipe supports
- Project team of 40+ personnel
- No LTI for 25,000 man hours


Chevron Wheatstone Project
Wenco is involved in the installation, testing and Pre-commissioning of Chevron Utility Water Line
Project Key Facts
Project Owner:
Chevron
Project Name:
Chevron Wheatstone Potable and Utility Water Project
Client:
Downer
WENCO Scope
-
GRE Piping Installation, testing and Pre-commissioning for 6kM Utility Water Pipeline.
PLUTO – GRE PIPING PROJECT
Wenco was awarded the Installation, testing and Pre-Commissioning of Pluto Aboveground Pipework
Project Key Facts
Project Owner:
Woodside
Project Name:
Pluto Potable & Utility water
Client:
Woodside
WENCO Scope
- Installation, testing and pre-Commissioning of the Above Ground GRE Piping – Potable water and Service Water
- Pre-fabrication at Wenco Workshop at Perth and Site Installation
- Removal of existing SS Pipes which has MIC (microbiological Induced Corrosion) and replaced with GRE for Better design Life and
- Installation of In-line valves & Bolt Torqueing.
- Installation of all pipe fixings to pipe supports.
- Installation, removal and reinstallation of specialty items and in-line instrumentation, including pressure safety valves and control valves, as required, after performing testing, flushing and Mechanical Completion activities.


YARA SCW Refurbishment Project (NOV-FGS)
Wenco was awarded the Installation, testing and Pre-Commissioning of Wheatstone Underground and Aboveground Pipework
Project Key Facts
Project Owner:
YARA
Project Name:
SCW Refurbishment Project
Client:
Clough - AMEC
WENCO Scope
- Supply, Pre-fabrication, Installation, Testing, Civil Works and Pre-commissioning of NOV FGS GRE & GRVe Pipes and Fittings
- Sea Cooling water – 6” to 72” Piping System
- Fresh Cooling water – 6” to 24” GRE Piping
- Removal of Existing GRE & GRVe Piping
- Installation of In-line valves & Bolt Torqueing.
- Installation of all pipe fixings to pipe supports.
- Installation, removal and reinstallation of specialty items and in-line instrumentation, including pressure safety valves and control valves, as required, after performing testing, flushing and Mechanical Completion



LAING O’ROURKE WHEATSTONE PIPING WORKS
Wenco was awarded the Installation, testing and Pre-Commissioning of Wheatstone Underground and Aboveground Pipework
Project Key Facts
Project Owner:
Chevron
Project Name:
WHEATSTONE A109 PIPING WORKS
Client:
Laing O'Rourke
WENCO Scope
- Installation, testing and pre-Commissioning of the Laing O’Rourke scope of works for the Wheatstone project Underground and Aboveground, Piping Installation (in accordance with document Scope of Works 109 Piping)
- Installation and Testing of Double containment Diesel Oil Pipes (Jacket) Carbon Steel DN 50(100) & 80(200)
- Installation and Testing of Fire Water, Utility, Potable Water Lines HDPE ( 50,80 & 500)
- Installation of In-line valves & Bolt Torqueing.
- Installation of all pipe fixings to pipe supports.
- Installation, removal and reinstallation of specialty items and in-line instrumentation, including pressure safety valves and control valves, as required, after performing testing, flushing and Mechanical Completion activities.


Chemical Injection Skid & Fire water replacement
Wenco was awarded multiple works including Waste Water Discharge Line, Fire Water Mist Line, Acid Line Replacement, Condensers blasting and painting of both CPP1 & CPP2
Project Key Facts
Project Owner:
YARA
Project Name:
CPP1, CPP2, Waste Water Discharge, Fire Water Mist
Client:
YARA
WENCO Scope
- Design, Supply and Install of GRE Pipes & Fittings
- Design, Supply and Install of Chemical Injection Skid Systems
- Design, Supply and Install of SS316 & SS304L Pipes & Fittings
- QA/QC & NDT Inspection Works
- Engineering design & Support
- Blasting (Dry & Wet Abrasive)
- Painting and Coating Works
- Concrete Repair Works
- Acid Line Skid Replacement with CPVC
- Fabricate and Install Fire Water Mist Line SS
- Fabricate and Install Waste Water Discharge Line (WWD)


BEENYUP WTP UPGRADE
Wenco was awarded the prestigious ‘Structural Mechanical Piping Package’ (SMP) including Feedwater, Strainers, UF, RO Plant, Degasser, Recycled Water PS & Chemical Area
Project Key Facts
Project Owner:
WATER CORP
Project Name:
Beenyup WTP Upgrade
Client:
KEP Alliance
WENCO Scope
- Supply and Install CS, UPVC, SS, HDPE, CS Pipes and Fittings
- Gaskets, Fasteners, Painting, Anchor bolts, Grouting & Chemical Injections
- Installation of Mechanical equipment & Structures – Pumps & Valves
- Supply & Install compressed air tubing from compressed air headers to actuated and control valves or solenoid valves
- Install Major pipe supports around the pumps, strainers and platforms
- Supply and install all equipment, valve and instrument tags as per project specification
- Installation of RO & UF Membranes
- Complete FEED water Pump area
- Complete Pressure test, Flush and clean out all pipelines and structures
- In-house design and Engineering
- Repair of Saddles


TAN BURRUP PROJECT ABOVE GROUND PIPE WORKS
Construction of an ammonium nitrate production facility on Karratha in Western Australia.
Wenco was appointed to supply a team to manage the installation of above ground metallic and non-metallic piping works
Project Key Facts
Project Owner:
Yara Pilbara Pty Ltd
Project Name:
Tan Burrup Project
Client:
Tecnicas Reunidas
Value (AUD:
$10 Million
WENCO Scope
- Onsite piping fabrication
- Onsite installation works
- Support installation
- Valve and equipment installation
- Hydro testing
- Project crew of 50
- Engineering QC
- Supervision support